United States › Grid › Interconnection queues › New Jersey
SOLAR · PJMMcCullough Road Solar Farm
McCullough Road Solar Farm is a 8.8 MW solar request built and operating in the PJM interconnection queue, in Warren County, New Jersey, connecting to JCPL.
Request details
- Queue ID
- W3-044
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- JCPL
- Connection point (POI)
- Washington 34.5kV
- Location
- Warren County, New Jersey
- Technology
- Solar: 8.8 MW
- Total requested
- 8.8 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 31 August 2010
- Proposed online date
- June 2019
- Came online
- June 2019
Location
Marker shows the centre of Warren County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Warren County
- Harmony Plains Solar and Storage FacilitySolar + storage · 70.0 MW · agreement signed
- Mansfield #3Battery storage · 20.0 MW · agreement signed
- Warren Glen StorageBattery storage · 20.0 MW · agreement signed
- Washington Solar PH IISolar · 11.0 MW · agreement signed
- Solar project AI1-137, Warren CountySolar · 155 MW · in study
- Solar project AI1-120, Warren CountySolar · 51.6 MW · in study
- Solar project AI1-118, Warren CountySolar · 37.6 MW · in study
- Solar project AI2-437, Warren CountySolar · 20.0 MW · in study
- Solar project AG2-625, Warren CountySolar · 19.6 MW · in study
- Kober Solar FarmSolar · 19.3 MW · in study
- Solar project AG2-626, Warren CountySolar · 12.5 MW · in study
- Alpha Battery Storage FacilityBattery storage · 20.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem