πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

GAS Β· CAISO

Pio Pico Plus

Pio Pico Plus is a 18.0 MW gas request built and operating in the CAISO interconnection queue, connecting to SDGE.

Queue statusOperating
  1. PlanningQueued Feb 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1348
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Otay Mesa Switchyard 230 kV
Location
California
Technology
Gas: 18.0 MW
Total requested
18.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
6 February 2017
Proposed online date
November 2017
Came online
October 2017

Location

No county location in the queue data.

Power plants in California Β· Transmission lines in California

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem