United States βΊ Grid βΊ Interconnection queues βΊ Utah
ONSHORE WIND Β· WESTOnshore wind project 736, Utah County
Onshore wind project 736, Utah County is a 175 MW onshore wind request withdrawn in the West interconnection queue, in Utah County, Utah, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 736
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Carbon-Spanish Fork #2 138 kV transmission line
- Location
- Utah County, Utah
- Technology
- Wind: 175 MW
- Total requested
- 175 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN BY CUSTOMER
- Queue status
- Withdrawn
- Entered queue
- 13 April 2016
- Proposed online date
- December 2019
Location
Marker shows the centre of Utah County; the queue data does not give exact sites.
Other requests in Utah County
- Solar + storage project 838, Utah CountySolar + storage Β· 525 MW Β· agreement signed
- Solar + storage project C1-34, Utah CountySolar + storage Β· 200 MW Β· agreement signed
- Solar + storage project T2-085, Utah CountySolar + storage Β· 400 MW Β· in study
- Solar + storage project T2-076, Utah CountySolar + storage Β· 400 MW Β· in study
- Gas project PIS040, Utah CountyGas Β· 300 MW Β· in study
- Gas project T2-059, Utah CountyGas Β· 300 MW Β· in study
- Gas project S0021, Utah CountyGas Β· 200 MW Β· in study
- Solar project PIS024, Utah CountySolar Β· 200 MW Β· in study
- Solar + storage project C2-57, Utah CountySolar + storage Β· 199 MW Β· in study
- Battery storage project C2-109, Utah CountyBattery storage Β· 199 MW Β· in study
- Solar + storage project T2-062, Utah CountySolar + storage Β· 199 MW Β· in study
- Battery storage project C2-110, Utah CountyBattery storage Β· 199 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem