🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

Dunn Siding Solar I

Dunn Siding Solar I is a 40.0 MW solar request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedSep 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
461
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Dunn Siding Cool Water 115 kV Line
Location
San Bernardino County, California
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 June 2008
Proposed online date
December 2010
Withdrawn
September 2008

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem