Solar project AH1-112, Kent County

Solar project AH1-112, Kent County is a 4.0 MW solar request withdrawn in the PJM interconnection queue, in Kent County, Delaware, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedNov 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-112
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
New Meredith 23 kV
Location
Kent County, Delaware
Technology
Solar: 4.0 MW
Total requested
4.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
6 August 2021
Proposed online date
April 2022
Withdrawn
November 2021

Location

Marker shows the centre of Kent County; the queue data does not give exact sites.

Power plants in Delaware Β· Transmission lines in Delaware

Other requests in Kent County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem