SOLAR Β· MISOSolar project J582, Madison Parish County
Solar project J582, Madison Parish County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Madison Parish County, Louisiana.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJul 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J582
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Madison Parish County, Louisiana
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 9 May 2016
- Proposed online date
- October 2018
- Withdrawn
- July 2017
Location
Marker shows the centre of Madison Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in Madison Parish County
- Onshore wind project J3273, Madison Parish CountyOnshore wind Β· 474 MW Β· withdrawn
- Solar project J3377, Madison Parish CountySolar Β· 150 MW Β· withdrawn
- Solar + storage project J3534, Madison Parish CountySolar + storage Β· 125 MW Β· withdrawn
- Solar project J1351, Madison Parish CountySolar Β· 120 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem