United States › Grid › Interconnection queues › Nebraska

ONSHORE WIND · SPP

Onshore wind project GEN-2015-088, Saline County

Onshore wind project GEN-2015-088, Saline County is a 300 MW onshore wind request built and operating in the SPP interconnection queue, in Saline County, Nebraska, connecting to NPPD.

Queue statusOperating
  1. PlanningQueued Sep 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-088
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Tobias 345kV Substation
Location
Saline County, Nebraska
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
30 September 2015
Proposed online date
December 2020
Came online
December 2020

Location

Marker shows the centre of Saline County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Saline County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem