United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR Β· SOUTHEASTSolar project LGE-GIS-2021-003, Ohio County
Solar project LGE-GIS-2021-003, Ohio County is a 150 MW solar request withdrawn in the Southeast interconnection queue, in Ohio County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2021 (completed)
- Withdrawn / abandonedAug 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2021-003
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Matanzas 138 kV Substation or Matanzas-Ohio County 138 kV line
- Location
- Ohio County, Kentucky
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 8 January 2021
- Proposed online date
- December 2023
- Withdrawn
- August 2021
Location
Marker shows the centre of Ohio County; the queue data does not give exact sites.
Other requests in Ohio County
- Solar project J2739, Ohio CountySolar Β· 100 MW Β· in study
- Solar + storage project J2282, Ohio CountySolar + storage Β· 100 MW Β· withdrawn
- Solar + storage project J2073, Ohio CountySolar + storage Β· 91.5 MW Β· withdrawn
- Solar + storage project J2137, Ohio CountySolar + storage Β· 78.2 MW Β· withdrawn
- Solar + storage project J2145, Ohio CountySolar + storage Β· 50.0 MW Β· withdrawn
- Other project LGE-GIS-2008-002, Ohio CountyOther Β· 5.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem