United States βΊ Grid βΊ Interconnection queues βΊ Michigan
ONSHORE WIND Β· MISOOnshore wind project J601, Lapeer County
Onshore wind project J601, Lapeer County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Lapeer County, Michigan.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJan 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J601
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Kilgore - Micah 120kV with the line distance 1 mile from Kilgore
- Location
- Lapeer County, Michigan
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Study phase
- GIA
- Queue status
- Withdrawn
- Entered queue
- 9 May 2016
- Proposed online date
- September 2018
- Withdrawn
- January 2018
Location
Marker shows the centre of Lapeer County; the queue data does not give exact sites.
Other requests in Lapeer County
- Onshore wind project J3866, Lapeer CountyOnshore wind Β· 300 MW Β· in study
- Solar project J3472, Lapeer CountySolar Β· 200 MW Β· in study
- Solar project J3828, Lapeer CountySolar Β· 100 MW Β· in study
- Solar project J1661, Lapeer CountySolar Β· 200 MW Β· withdrawn
- Solar project J3876, Lapeer CountySolar Β· 150 MW Β· withdrawn
- Solar project J839, Lapeer CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J3875, Lapeer CountyBattery storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem