United States › Grid › Interconnection queues › New York
ONSHORE WIND · NYISOParagon I Wind Generation
Paragon I Wind Generation is a 100 MW onshore wind request withdrawn in the NYISO interconnection queue, in Steuben County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2005 (completed)
- Withdrawn / abandonedAug 2008 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 163
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Clipper Windpower Dev. Co. Inc.
- Connection point (POI)
- Bath-Montour Falls 115kV
- Location
- Steuben County, New York
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Queue status
- Withdrawn
- Entered queue
- 13 January 2005
- Withdrawn
- August 2008
Location
Marker shows the centre of Steuben County; the queue data does not give exact sites.
Other requests in Steuben County
- Canisteo WindOnshore wind · 291 MW · in study
- Gemma Energy StorageBattery storage · 200 MW · in study
- Prattsburgh Wind FarmOnshore wind · 147 MW · in study
- CohoctonSolar + storage · 130 MW · in study
- Bassett Energy StorageBattery storage · 79.9 MW · in study
- Clear View SolarSolar · 20.0 MW · in study
- Baron WindsOnshore wind · 239 MW · built
- Baron WindsOnshore wind · 239 MW · built
- Morris Ridge Solar Energy CenterSolar · 177 MW · built
- Morris Ridge Solar Energy CenterSolar · 177 MW · built
- Eight Point Wind Energy CenterOnshore wind · 102 MW · built
- Canandaigua Wind FarmOnshore wind · 82.5 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem