United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
COAL Β· PJMMontour #2
Montour #2 is a 7.0 MW coal request built and operating in the PJM interconnection queue, in Montour County, Pennsylvania, connecting to PPL.
Request details
- Queue ID
- E07
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Montour 230kV
- Location
- Montour County, Pennsylvania
- Technology
- Coal: 7.0 MW
- Total requested
- 7.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 6 October 2000
- Proposed online date
- January 1999
- Came online
- May 2002
Location
Marker shows the centre of Montour County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Montour County
- Solar project AI2-475, Montour CountySolar Β· 40.6 MW Β· in study
- Solar project AI2-474, Montour CountySolar Β· 34.8 MW Β· in study
- Solar project AI2-471, Montour CountySolar Β· 29.5 MW Β· in study
- Solar project AI2-473, Montour CountySolar Β· 29.0 MW Β· in study
- Solar project AI2-472, Montour CountySolar Β· 14.5 MW Β· in study
- Montour #2Coal Β· 14.0 MW Β· built
- Montour #1Coal Β· 14.0 MW Β· built
- Montour #1Coal Β· 2.0 MW Β· built
- Nuclear project R01, Montour CountyNuclear Β· 800 MW Β· withdrawn
- Solar project AF1-311, Montour CountySolar Β· 150 MW Β· withdrawn
- Montour Solar OneSolar Β· 102 MW Β· withdrawn
- Solar project AE1-224, Montour CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem