United States βΊ Grid βΊ Interconnection queues βΊ West Virginia
ONSHORE WIND Β· PJMOnshore wind project V3-027, Webster County
Onshore wind project V3-027, Webster County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Webster County, West Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2009 (completed)
- Withdrawn / abandonedFeb 2010 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- V3-027
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Pickens 138kV
- Location
- Webster County, West Virginia
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 August 2009
- Proposed online date
- December 2013
- Withdrawn
- February 2010
Location
Marker shows the centre of Webster County; the queue data does not give exact sites.
Power plants in West Virginia Β· Transmission lines in West Virginia
Other requests in Webster County