AD-Chambersburg

AD-Chambersburg is a 2.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Adams County, Pennsylvania, connecting to ME.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandonedApr 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF2-268
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ME
Connection point (POI)
Orrtanna 13.2 kV
Location
Adams County, Pennsylvania
Technology
Solar: 2.0 MW · Battery
Total requested
2.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
27 March 2020
Proposed online date
September 2022
Withdrawn
April 2024

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem