United States β€Ί Grid β€Ί Interconnection queues β€Ί California

GAS Β· CAISO

Algonquin Power Sanger 2

Algonquin Power Sanger 2 is a 108 MW gas request withdrawn in the CAISO interconnection queue, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2013 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. ConsentedDec 2015 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
955
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Sanger Co-gen 115/13.8kV Sub
Location
California
Technology
Gas: 108 MW
Total requested
108 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Withdrawn
Entered queue
30 April 2013
Agreement signed
9 December 2015
Proposed online date
November 2020
Withdrawn
April 2020

Location

No county location in the queue data.

Power plants in California Β· Transmission lines in California

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem