United States βΊ Grid βΊ Interconnection queues βΊ Georgia
SOLAR Β· SOUTHEASTSolar project IC-677, Seminole County
Solar project IC-677, Seminole County is a 150 MW solar request withdrawn in the Southeast interconnection queue, in Seminole County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedMar 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-677
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- East Bainbridge - Spring Creek (Black) 115 kV Line
- Location
- Seminole County, Georgia
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 8 March 2018
- Withdrawn
- March 2019
Location
Marker shows the centre of Seminole County; the queue data does not give exact sites.
Other requests in Seminole County
- Solar + storage project 25-IC-AZ, Seminole CountySolar + storage Β· 100 MW Β· withdrawn
- Solar + storage project IC-1027, Seminole CountySolar + storage Β· 90.0 MW Β· withdrawn
- Solar project IC-1115, Seminole CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-607, Seminole CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-328, Seminole CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem