πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· WEST

Solar project SRP-Q20

Solar project SRP-Q20 is a 20.0 MW solar request built and operating in the West interconnection queue, connecting to Salt River Project.

Queue statusOperating
  1. PlanningQueued Nov 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Jul 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SRP-Q20
Grid region
West (non-ISO utilities)
Utility / transmission owner
Salt River Project
Connection point (POI)
Germann 69 kV
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
15 November 2010
Proposed online date
July 2012

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in Β· Transmission lines in

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem