SOLAR + STORAGE · PJM

Solar + storage project AG2-420, Venango County

Solar + storage project AG2-420, Venango County is a 25.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Venango County, Pennsylvania, connecting to PENELEC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-420
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Developer
Bear Oak Solar LLC
Connection point (POI)
Eclipse #2 34.5 kV
Location
Venango County, Pennsylvania
Technology
Solar: 25.0 MW · Battery
Total requested
25.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
13 March 2025
Proposed online date
May 2023

Location

Marker shows the centre of Venango County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Venango County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem