SOLAR Β· NYISO

Calverton Solar Energy Center

Calverton Solar Energy Center is a 22.9 MW solar request built and operating in the NYISO interconnection queue, connecting to LIPA.

Queue statusOperating
  1. PlanningQueued Oct 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
678
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
LI Solar Generation, LLC
Connection point (POI)
Edwards Substation 138kV
Location
New York
Technology
Solar: 22.9 MW
Total requested
22.9 MW
Study phase
SIS, FS
Queue status
Operational
Entered queue
26 October 2017

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem