United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTPequin Energy Storage
Pequin Energy Storage is a 103 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Brazoria County, Texas.
Queue statusIn planning
- PlanningQueued Jan 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 23INR0194
- Grid region
- ERCOT (Texas)
- Developer
- Pequin Energy Storage, LLC
- Connection point (POI)
- 39500 TN West Columbia 138kV
- Location
- Brazoria County, Texas
- Technology
- Battery: 103 MW
- Total requested
- 103 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 25 January 2021
- Proposed online date
- September 2027
Location
Marker shows the centre of Brazoria County; the queue data does not give exact sites.
Other requests in Brazoria County
- Austin Bayou SolarSolar + storage · 503 MW · agreement signed
- Gamay Energy StorageBattery storage · 419 MW · agreement signed
- Aldrin 345 BESSBattery storage · 362 MW · agreement signed
- Cottonwood Bayou SolarSolar · 351 MW · agreement signed
- Myrtle SolarSolar · 321 MW · agreement signed
- Elio BESSBattery storage · 317 MW · agreement signed
- First Capitol BESSBattery storage · 258 MW · agreement signed
- Hastings Park BESSBattery storage · 256 MW · agreement signed
- Clutch City Solar Phase IISolar · 251 MW · agreement signed
- Tanglewood SolarSolar · 251 MW · agreement signed
- Aldrin 138 BESSBattery storage · 207 MW · agreement signed
- Desna BESSBattery storage · 206 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem