United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

Live Oak Solar

Live Oak Solar is a 51.0 MW solar request built and operating in the Southeast interconnection queue, in Candler County, Georgia, connecting to Southern Company.

Queue statusOperating
  1. Planning (completed)
  2. ConsentedSep 2015 (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IC-364
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Location
Candler County, Georgia
Technology
Solar: 51.0 MW
Total requested
51.0 MW
Study phase
Operational
Queue status
Operational
Agreement signed
11 September 2015
Came online
December 2016

Location

Marker shows the centre of Candler County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Candler County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem