Hartley Battery Storage

Hartley Battery Storage is a 20.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Orange County, New York, connecting to O&R.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
916
Grid region
NYISO (New York)
Utility / transmission owner
O&R
Developer
EDF Renewables Development, Inc.
Connection point (POI)
Hartley Road Substation 69kV
Location
Orange County, New York
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
7 October 2019
Withdrawn
March 2020

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Orange County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem