United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

SOSA Storage

SOSA Storage is a 155 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Madison County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2022 (completed)
  2. ConsentedDec 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0131
Grid region
ERCOT (Texas)
Developer
Sosa Energy Center, LLC
Connection point (POI)
Tap 138kV 25 North Zulch - 47 Hilltop Lakes
Location
Madison County, Texas
Technology
Battery: 155 MW
Total requested
155 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
25 July 2022
Agreement signed
5 December 2023
Proposed online date
July 2027

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem