United States › Grid › Interconnection queues › Virginia

HYDRO · PJM

Reusens Hydro Electric Generating Plant

Reusens Hydro Electric Generating Plant is a 12.5 MW hydro request built and operating in the PJM interconnection queue, in City Of Lynchburg County, Virginia, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Apr 2016 (completed)
  2. ConsentedFeb 2017 (completed)
  3. Construction (completed)
  4. OperatingNov 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB2-109
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Reusens 34.5kV
Location
City Of Lynchburg County, Virginia
Technology
Hydro: 12.5 MW
Total requested
12.5 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
28 April 2016
Agreement signed
20 February 2017
Proposed online date
March 2018
Came online
November 2017

Location

Marker shows the centre of City Of Lynchburg County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in City Of Lynchburg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem