HYDRO · PJMReusens Hydro Electric Generating Plant
Reusens Hydro Electric Generating Plant is a 12.5 MW hydro request built and operating in the PJM interconnection queue, in City Of Lynchburg County, Virginia, connecting to AEP.
Request details
- Queue ID
- AB2-109
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Reusens 34.5kV
- Location
- City Of Lynchburg County, Virginia
- Technology
- Hydro: 12.5 MW
- Total requested
- 12.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 28 April 2016
- Agreement signed
- 20 February 2017
- Proposed online date
- March 2018
- Came online
- November 2017
Location
Marker shows the centre of City Of Lynchburg County; the queue data does not give exact sites.
Other requests in City Of Lynchburg County
- Battery storage project AG2-202, City Of Lynchburg CountyBattery storage · 20.0 MW · withdrawn
- Battery storage project AG2-203, City Of Lynchburg CountyBattery storage · 20.0 MW · withdrawn
- Other project Y3-119, City Of Lynchburg CountyOther · 19.0 MW · withdrawn
- CO-Zaners RohrsburgSolar + storage · 3.0 MW · withdrawn
- LH ChurchSolar + storage · 3.0 MW · withdrawn
- CO-RidgeSolar + storage · 2.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem