SOLAR Β· MISO

Solar project J1240, Audrain County

Solar project J1240, Audrain County is a 135 MW solar request withdrawn in the MISO interconnection queue, in Audrain County, Missouri, connecting to Ameren Missouri.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedNov 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1240
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Spencer Creek 345kV Substation
Location
Audrain County, Missouri
Technology
Solar: 135 MW
Total requested
135 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
September 2022
Withdrawn
November 2019

Location

Marker shows the centre of Audrain County; the queue data does not give exact sites.