United States › Grid › Interconnection queues › Texas
GAS · ERCOTBeachwood Power Station (Mark One)
Beachwood Power Station (Mark One) is a 153 MW gas request built and operating in the ERCOT interconnection queue, in Brazoria County, Texas.
Request details
- Queue ID
- 22INR0369
- Grid region
- ERCOT (Texas)
- Developer
- WattBridge Energy, LLC
- Connection point (POI)
- 42110 Angleton 138kV
- Location
- Brazoria County, Texas
- Technology
- Gas: 153 MW
- Total requested
- 153 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 9 July 2020
- Agreement signed
- 21 July 2021
- Proposed online date
- October 2022
- Came online
- November 2022
Location
Marker shows the centre of Brazoria County; the queue data does not give exact sites.
Other requests in Brazoria County
- Austin Bayou SolarSolar + storage · 503 MW · agreement signed
- Gamay Energy StorageBattery storage · 419 MW · agreement signed
- Aldrin 345 BESSBattery storage · 362 MW · agreement signed
- Cottonwood Bayou SolarSolar · 351 MW · agreement signed
- Myrtle SolarSolar · 321 MW · agreement signed
- Elio BESSBattery storage · 317 MW · agreement signed
- First Capitol BESSBattery storage · 258 MW · agreement signed
- Hastings Park BESSBattery storage · 256 MW · agreement signed
- Clutch City Solar Phase IISolar · 251 MW · agreement signed
- Tanglewood SolarSolar · 251 MW · agreement signed
- Aldrin 138 BESSBattery storage · 207 MW · agreement signed
- Desna BESSBattery storage · 206 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem