United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
ONSHORE WIND Β· PJMOnshore wind project AB1-077, Perquimans County
Onshore wind project AB1-077, Perquimans County is a 150 MW onshore wind request withdrawn in the PJM interconnection queue, in Perquimans County, North Carolina, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2015 (completed)
- Withdrawn / abandonedNov 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AB1-077
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Suffolk-WinFall 230kV
- Location
- Perquimans County, North Carolina
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 21 September 2015
- Proposed online date
- December 2019
- Withdrawn
- November 2016
Location
Marker shows the centre of Perquimans County; the queue data does not give exact sites.
Power plants in North Carolina Β· Transmission lines in North Carolina
Other requests in Perquimans County
- Timbermill Wind FarmOnshore wind Β· 189 MW Β· built
- Solar project AE2-147, Perquimans CountySolar Β· 150 MW Β· withdrawn
- Solar project AC2-194, Perquimans CountySolar Β· 16.2 MW Β· withdrawn
- South Hertford SolarSolar Β· 5.0 MW Β· withdrawn
- Solar project AB2-186, Perquimans CountySolar Β· 5.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem