7V Solar

7V Solar is a 241 MW solar request built and operating in the ERCOT interconnection queue, in Fayette County, Texas.

Queue statusOperating
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedSep 2020 (completed)
  3. Construction (completed)
  4. OperatingJan 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0351
Grid region
ERCOT (Texas)
Developer
7V Solar Ranch, LLC
Connection point (POI)
tap 138kV 7248 Flatonia - 7274 Plum
Location
Fayette County, Texas
Technology
Solar: 241 MW
Total requested
241 MW
Study phase
IA
Queue status
Operational
Entered queue
15 April 2019
Agreement signed
1 September 2020
Proposed online date
February 2025
Came online
January 2025

Location

Marker shows the centre of Fayette County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Fayette County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem