BATTERY STORAGE · NYISO

Bloom Energy Storage Center

Bloom Energy Storage Center is a 120 MW battery storage request withdrawn in the NYISO interconnection queue, in Kings County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
845
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
sPower Development Company, LLC
Connection point (POI)
Farragut 345kV Substation
Location
Kings County, New York
Technology
Battery: 120 MW
Total requested
120 MW
Queue status
Withdrawn
Entered queue
20 May 2019
Withdrawn
March 2020

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Kings County