United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project J4125, Bay County

Onshore wind project J4125, Bay County is a 50.0 MW onshore wind request in interconnection study in the MISO interconnection queue, in Bay County, Michigan, connecting to ITC.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4125
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
Other_
Location
Bay County, Michigan
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
16 September 2025
Proposed online date
October 2030

Location

Marker shows the centre of Bay County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Bay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem