🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project J3361, Bay County

Onshore wind project J3361, Bay County is a 254 MW onshore wind request in interconnection study in the MISO interconnection queue, in Bay County, Michigan.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3361
Grid region
MISO (Midcontinent)
Connection point (POI)
Other_
Location
Bay County, Michigan
Technology
Wind: 254 MW
Total requested
254 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
12 April 2024
Proposed online date
December 2027

Location

Marker shows the centre of Bay County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Bay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem