United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
ONSHORE WIND Β· SPPOnshore wind project GEN-2013-018, Otoe County
Onshore wind project GEN-2013-018, Otoe County is a 51.0 MW onshore wind request withdrawn in the SPP interconnection queue, in Otoe County, Nebraska, connecting to OPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2013 (completed)
- Withdrawn / abandonedOct 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2013-018
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Tap S974 - Hydrocarbon Tap 69kV
- Location
- Otoe County, Nebraska
- Technology
- Wind: 51.0 MW
- Total requested
- 51.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 April 2013
- Proposed online date
- October 2014
- Withdrawn
- October 2013
Location
Marker shows the centre of Otoe County; the queue data does not give exact sites.
Other requests in Otoe County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem