United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

Winergy Long Island Wind

Winergy Long Island Wind is a 299 MW onshore wind request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandonedJul 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
273
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Winergy Power, LLC
Connection point (POI)
Sterling Substation
Location
Suffolk County, New York
Technology
Wind: 299 MW
Total requested
299 MW
Queue status
Withdrawn
Entered queue
21 December 2007
Withdrawn
July 2008

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Suffolk County