Lost Hills Solar

Lost Hills Solar is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in San Francisco County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Jun 2009 (completed)
  2. ConsentedMar 2011 (completed)
  3. Construction (completed)
  4. OperatingApr 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
484
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Arco-Carneras 70 kV Line
Location
San Francisco County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
11 June 2009
Agreement signed
24 March 2011
Proposed online date
December 2013
Came online
April 2015

Location

Marker shows the centre of San Francisco County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Francisco County