Solar Star Xi

Solar Star Xi is a 70.0 MW solar request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2010 (completed)
  2. Withdrawn / abandonedMar 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
578
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Cottonwood-Savage 115kV line
Location
San Bernardino County, California
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 February 2010
Proposed online date
December 2013
Withdrawn
March 2010

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.