High Chap Solar

High Chap Solar is a 152 MW solar request withdrawn in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2022 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. ConsentedNov 2023 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0068
Grid region
ERCOT (Texas)
Developer
HIGH CHAPARRAL SOLAR PROJECT LLC
Connection point (POI)
43035 Oasis 345kV - 42500 Dow Chemical 345 kV Ckt 18
Location
Brazoria County, Texas
Technology
Solar: 152 MW
Total requested
152 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
4 July 2022
Agreement signed
21 November 2023
Proposed online date
June 2028
Withdrawn
December 2025

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem