🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Opal Storage Project

Opal Storage Project is a 200 MW battery storage request withdrawn in the NYISO interconnection queue, in Orange County, New York, connecting to CHG&E.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1306
Grid region
NYISO (New York)
Utility / transmission owner
CHG&E
Developer
Hanwha Q CELLS USA
Connection point (POI)
East Walden 115 kV substation
Location
Orange County, New York
Technology
Battery: 200 MW
Total requested
200 MW
Queue status
Withdrawn
Entered queue
12 November 2021

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Orange County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem