United States › Grid › Interconnection queues › Kansas

ONSHORE WIND · SPP

Onshore wind project GEN-2015-065, Thomas County

Onshore wind project GEN-2015-065, Thomas County is a 202 MW onshore wind request built and operating in the SPP interconnection queue, in Thomas County, Kansas, connecting to SUNC.

Queue statusOperating
  1. PlanningQueued Oct 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-065
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Mingo 345kV
Location
Thomas County, Kansas
Technology
Wind: 202 MW
Total requested
202 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
7 October 2015
Proposed online date
July 2019
Came online
July 2019

Location

Marker shows the centre of Thomas County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Thomas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem