United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR Β· MISOSolar project J1854, Wabash County
Solar project J1854, Wabash County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Wabash County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedDec 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1854
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Wabash - Greentown 138kV
- Location
- Wabash County, Indiana
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2
- Queue status
- Withdrawn
- Entered queue
- 18 August 2021
- Proposed online date
- May 2025
- Withdrawn
- December 2021
Location
Marker shows the centre of Wabash County; the queue data does not give exact sites.
Other requests in Wabash County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem