ONSHORE WIND Β· MISOOnshore wind project J983, Brown County
Onshore wind project J983, Brown County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Brown County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedNov 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J983
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Oglesby - Minonk Tap 138kV Line Tap
- Location
- Brown County, Illinois
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Proposed online date
- March 2021
- Withdrawn
- November 2018
Location
Marker shows the centre of Brown County; the queue data does not give exact sites.
Other requests in Brown County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem