ONSHORE WIND Β· MISO

Onshore wind project J983, Brown County

Onshore wind project J983, Brown County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Brown County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedNov 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J983
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Oglesby - Minonk Tap 138kV Line Tap
Location
Brown County, Illinois
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
March 2021
Withdrawn
November 2018

Location

Marker shows the centre of Brown County; the queue data does not give exact sites.