United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
SOLAR Β· MISOSolar project J2354, Marinette County
Solar project J2354, Marinette County is a 65.0 MW solar request withdrawn in the MISO interconnection queue, in Marinette County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2354
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Crivitz
- Location
- Marinette County, Wisconsin
- Technology
- Solar: 65.0 MW
- Total requested
- 65.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- December 2024
- Withdrawn
- July 2025
Location
Marker shows the centre of Marinette County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Marinette County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem