ONSHORE WIND Β· SPP

Onshore wind project GEN-2024-112, Washita County

Onshore wind project GEN-2024-112, Washita County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Washita County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-112
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Chisholm - Gracemont 345 kV line
Location
Washita County, Oklahoma
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
1 March 2025
Proposed online date
December 2031
Withdrawn
August 2025

Location

Marker shows the centre of Washita County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Washita County