Onshore wind project IA-PNM-2003-01, Guadaloupe County

Onshore wind project IA-PNM-2003-01, Guadaloupe County is a 90.0 MW onshore wind request built and operating in the West interconnection queue, in Guadaloupe County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. Planning (completed)
  2. ConsentedDec 2005 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IA-PNM-2003-01
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Aragonne Mesa
Location
Guadaloupe County, New Mexico
Technology
Wind: 90.0 MW
Total requested
90.0 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Agreement signed
21 December 2005

Location

Marker shows the centre of Guadaloupe County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Guadaloupe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem