United States βΊ Grid βΊ Interconnection queues βΊ Texas
BATTERY STORAGE Β· MISOBattery storage project J1907, Newton County
Battery storage project J1907, Newton County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Newton County, Texas, connecting to ENTERGY TEXAS, INC..
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedMar 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1907
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY TEXAS, INC.
- Connection point (POI)
- Other
- Location
- Newton County, Texas
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 August 2021
- Proposed online date
- December 2022
- Withdrawn
- March 2025
Location
Marker shows the centre of Newton County; the queue data does not give exact sites.
Other requests in Newton County
- Solar project J2629, Newton CountySolar Β· 175 MW Β· in study
- Gas project J539, Newton CountyGas Β· 999 MW Β· withdrawn
- Solar project J3409, Newton CountySolar Β· 400 MW Β· withdrawn
- Gas project J369, Newton CountyGas Β· 393 MW Β· withdrawn
- Solar + storage project J2688, Newton CountySolar + storage Β· 130 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem