ONSHORE WIND Β· SPP

Onshore wind project GEN-2022-195, Harper County

Onshore wind project GEN-2022-195, Harper County is a 145 MW onshore wind request withdrawn in the SPP interconnection queue, in Harper County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-195
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Viola 345 kV Substation
Location
Harper County, Kansas
Technology
Wind: 145 MW
Total requested
145 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 February 2023
Proposed online date
December 2028
Withdrawn
November 2023

Location

Marker shows the centre of Harper County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Harper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem