South Pier Improvement

South Pier Improvement is a 108 MW gas request withdrawn in the NYISO interconnection queue, in Kings County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2007 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
261
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Astoria Generating Company
Connection point (POI)
Gowanus 138kV
Location
Kings County, New York
Technology
Gas: 108 MW
Total requested
108 MW
Queue status
Withdrawn
Entered queue
2 October 2007
Withdrawn
March 2012

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem