United States › Grid › Interconnection queues › Utah
SOLAR + STORAGE · WESTSolar + storage project C1-51, Juab County
Solar + storage project C1-51, Juab County is a 300 MW solar + storage request suspended in the West interconnection queue, in Juab County, Utah, connecting to PacifiCorp.
Queue statusPaused / redesign
- PlanningQueued May 2021 (current stage)
- ConsentedMay 2023 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C1-51
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Thirsty Valley Solar Energy LLC
- Connection point (POI)
- Clover substation
- Location
- Juab County, Utah
- Technology
- Solar: 300 MW · Battery
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- LGIA executed 5/25/2023, suspended 10/26/2023
- Queue status
- Suspended
- Entered queue
- 14 May 2021
- Agreement signed
- 25 May 2023
- Proposed online date
- October 2024
Location
Marker shows the centre of Juab County; the queue data does not give exact sites.
Other requests in Juab County
- Solar + storage project Q114, Juab CountySolar + storage · 690 MW · in study
- Solar + storage project Q85, Juab CountySolar + storage · 550 MW · in study
- Gas project T2-020, Juab CountyGas · 363 MW · in study
- Solar + storage project T2-056, Juab CountySolar + storage · 300 MW · in study
- Solar + storage project PIS047, Juab CountySolar + storage · 275 MW · in study
- Solar + storage project T2-023, Juab CountySolar + storage · 275 MW · in study
- Gas project C2-05, Juab CountyGas · 200 MW · in study
- Gas project PIS009, Juab CountyGas · 200 MW · in study
- Gas project PIS012, Juab CountyGas · 200 MW · in study
- Gas project C2-02, Juab CountyGas · 200 MW · in study
- Solar + storage project 785, Juab CountySolar + storage · 199 MW · in study
- Solar + storage project T2-055, Juab CountySolar + storage · 175 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem