πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2024-116, Hughes County

Solar + storage project GEN-2024-116, Hughes County is a 199 MW solar + storage request withdrawn in the SPP interconnection queue, in Hughes County, Oklahoma, connecting to SWPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-116
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SWPA
Connection point (POI)
Weleetka - Greasy Creek 138 kV Line
Location
Hughes County, Oklahoma
Technology
Solar: 199 MW Β· Battery
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
1 March 2025
Proposed online date
December 2028
Withdrawn
December 2025

Location

Marker shows the centre of Hughes County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Hughes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem