United States βΊ Grid βΊ Interconnection queues βΊ New Mexico
GAS Β· WESTGas project IA-PNM-2007-02, Bernalillo Cty County
Gas project IA-PNM-2007-02, Bernalillo Cty County is a 90.0 MW gas request withdrawn in the West interconnection queue, in Bernalillo Cty County, New Mexico, connecting to Public Service Company of New Mexico.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2007 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedJul 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IA-PNM-2007-02
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company of New Mexico
- Connection point (POI)
- Delta-Person
- Location
- Bernalillo Cty County, New Mexico
- Technology
- Gas: 90.0 MW
- Total requested
- 90.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- LGIA executed 10/28/2008. Terminated.
- Queue status
- Withdrawn
- Entered queue
- 2 March 2007
- Agreement signed
- 30 July 2014
- Proposed online date
- February 2015
Location
Marker shows the centre of Bernalillo Cty County; the queue data does not give exact sites.
Power plants in New Mexico Β· Transmission lines in New Mexico
Other requests in Bernalillo Cty County
- Solar + storage project IA-PNM-2020-04, Bernalillo CountySolar + storage Β· 400 MW Β· agreement signed
- Solar + storage project IA-PNM-2021-10, Bernalillo CountySolar + storage Β· 300 MW Β· agreement signed
- Juan Tabo GridBattery storage Β· 200 MW Β· agreement signed
- Sun Lasso Energy CenterBattery storage Β· 153 MW Β· agreement signed
- Solar + storage project IA-PNM-2021-09, Bernalillo CountySolar + storage Β· 150 MW Β· agreement signed
- Corazon Energy StorageBattery storage Β· 150 MW Β· agreement signed
- Battery storage project IA-PNM-2019-19, Bernalillo CountyBattery storage Β· 150 MW Β· agreement signed
- Battery storage project IA-PNM-2020-17, Bernalillo CountyBattery storage Β· 150 MW Β· agreement signed
- Zinnia StorageBattery storage Β· 100 MW Β· agreement signed
- Zinnia StorageBattery storage Β· 50.0 MW Β· agreement signed
- Solar + storage project IA-PNM-2025-10, Bernalillo CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project IA-PNM-2025-04, Bernalillo CountySolar + storage Β· 250 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem