Dry Lots Wind

Dry Lots Wind is a 33.0 MW onshore wind request withdrawn in the NYISO interconnection queue, in Herkimer County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2011 (completed)
  2. Withdrawn / abandonedFeb 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
372
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Dry Lots Wind, LLC
Connection point (POI)
Schuyler - Whitesboro 46kV
Location
Herkimer County, New York
Technology
Wind: 33.0 MW
Total requested
33.0 MW
Queue status
Withdrawn
Entered queue
31 October 2011
Withdrawn
February 2021

Location

Marker shows the centre of Herkimer County; the queue data does not give exact sites.