United States › Grid › Interconnection queues › New York
ONSHORE WIND · NYISOClinton II Windfield
Clinton II Windfield is a 21.0 MW onshore wind request built and operating in the NYISO interconnection queue, in Clinton County, New York, connecting to NYPA.
Request details
- Queue ID
- 211
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Noble Environmental Power, LLC
- Connection point (POI)
- Willis-Plattsburgh WP-2 230kV
- Location
- Clinton County, New York
- Technology
- Wind: 21.0 MW
- Total requested
- 21.0 MW
- Study phase
- SRIS, CY07
- Queue status
- Operational
- Entered queue
- 3 April 2006
- Came online
- October 2008
Location
Marker shows the centre of Clinton County; the queue data does not give exact sites.
Other requests in Clinton County
- Bull Run II WindOnshore wind · 449 MW · in study
- Valcour StorageBattery storage · 150 MW · in study
- Leo Energy StorageBattery storage · 75.0 MW · in study
- Marble River II Wind FarmOnshore wind · 132 MW · built
- Marble River II Wind FarmOnshore wind · 132 MW · built
- Altona WindfieldOnshore wind · 99.0 MW · built
- Altona WindfieldOnshore wind · 99.0 MW · built
- Marble River Wind FarmOnshore wind · 83.0 MW · built
- Marble River Wind FarmOnshore wind · 83.0 MW · built
- Ellenburg WindfieldOnshore wind · 81.0 MW · built
- Ellenburg WindfieldOnshore wind · 81.0 MW · built
- Clinton WindfieldOnshore wind · 79.5 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem